Which of the following is NOT the alternative of optimizing risk management?
A.
Risk avoidance
B.
Risk assessment
C.
Risk transfer
D.
Risk spreading
The Answer Is:
B
This question includes an explanation.
Explanation:
Risk assessment is a foundational step within the risk management process—not an alternative to managing risk. Alternatives to optimize risk management include:
Risk avoidance: eliminating the activity causing the risk
Risk transfer: shifting the risk to another party (e.g., through insurance)
Risk spreading: distributing the risk to reduce overall impact
Risk assessment, in contrast, is the evaluation of threats and vulnerabilities and precedes these treatment decisions.
References from PSP: Risk Treatment Options – ASIS POA; PSP Study Guide – Risk Management and Analysis
ASIS-PSP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"