An owner's acceptance of a security system marks the beginning of:
A.
The warranty period
B.
Phase II assessment
C.
Phase II testing
D.
Site acceptance testing
The Answer Is:
A
This question includes an explanation.
Explanation:
The owner’s formal acceptance of a security system—usually after site acceptance testing—is the point at which the warranty period typically begins. From this moment, the vendor or contractor is responsible for addressing defects or performance issues as stipulated in the contract.
B and C (Phase II references) are not standard project stages.
D (Site acceptance testing) occurs before acceptance and warranty activation.
[References:, PSP Study Guide – Project Phases and System Acceptance, POA Manual – Contractual Obligations and Warranty Initiation]
ASIS-PSP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"