An initial system administration training class should be conducted at approximately 30 days:
A.
Before site acceptance testing
B.
After site acceptance testing
C.
Before reliability testing
D.
After reliability testing
The Answer Is:
B
This question includes an explanation.
Explanation:
System administration training should occur after site acceptance testing (SAT), which confirms that the system performs as specified. At this point, the system is stable and ready for operational use, making it the right time to train administrators on real equipment in a functional environment.
Training before SAT (A or C) risks using incomplete systems.
D (After reliability testing) may delay training unnecessarily.
[References:, PSP Study Guide – Security System Implementation and Training, POA Manual – Security Technology Deployment Practices, ]
ASIS-PSP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"