A major result of conducting a business impact analysis is identifying:
A.
Recovery strategies
B.
Mitigation alternatives
C.
Critical functions
D.
Replacement agreements
The Answer Is:
C
This question includes an explanation.
Explanation:
A Business Impact Analysis (BIA) is a core component of business continuity planning. Its primary outcome is the identification of critical business functions and processes—those that are essential to the organization’s survival and need to be restored first after a disruption. This lays the groundwork for selecting appropriate recovery strategies and prioritizing resources.
A (Recovery strategies) are developed after identifying critical functions.
B (Mitigation alternatives) are part of risk treatment but not the direct result of BIA.
D (Replacement agreements) may be used later in continuity planning.
[References:, PSP Study Guide – Business Continuity and BIA, POA Manual – Business Continuity Planning Process, ]
ASIS-PSP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"