A crisis management team has been activated because a facility has suffered major hurricane damage.

A crisis management team has been activated because a facility has suffered major hurricane damage. What is the next step in the business continuity process?

A.

Damage assessment

B.

Stakeholder communications

C.

Alternate work site activation

D.

Response to media