Which of the following statements about estimating is true?
Post project reviews are a prime source of estimating data.
An estimated cost for a project must be 10 per cent to be any use
If you cannot estimate task durations to within 20 per cent there is no point in developing a schedule.
The project manager should always add 10 cent to peoples duration estimates to allow for natural optimism