One of the reasons a project life cycle is split into phases is to:

One of the reasons a project life cycle is split into phases is to:

A.

facilitate formal go/no-go decision making during the project.

B.

balance the costs of work in each phase of project development.

C.

mirror the major deployments of resources throughout the project.

D.

chunk work into time periods of similar durations.