APM APM-PFQ Question Answer
Which one of the following is NOT a project change?
An approved omission from the agreed project scope.
The potential for agreed resources to be removed from the project.
A. requirement for extra expenditure to cover increased supplier costs.
The removal of work packages from the agreed project scope.