APM APM-PFQ Question Answer
A key output of a well-controlled configuration management process is:
documented traceability between versions of each configuration item.
that the project is most likely to meet its success criteria.
documented evidence of all project changes: proposed. authorised, rejected or deferred.
an agreed point after which no further changes to scope will be considered.