A key output of a well-controlled configuration management process is:

A key output of a well-controlled configuration management process is:

A.

documented traceability between versions of each configuration item.

B.

that the project is most likely to meet its success criteria.

C.

documented evidence of all project changes: proposed. authorised, rejected or deferred.

D.

an agreed point after which no further changes to scope will be considered.