What will affect the level of risk mitigation achieved in RBI?
A.
The established frequency of inspection for higher risk equipment
B.
The quality of the inspection data and the analysis or interpretation of that data
C.
Replacement of equipment instead of continuing to inspect it after half-life is attained
D.
Upgrading the metallurgy of equipment to higher alloys which are more corrosion resistant
The Answer Is:
B
This question includes an explanation.
Explanation:
According to API 580 Section 12.1:
"Risk mitigation (by the reduction in uncertainty) achieved through inspection presumes that the organization will act on the results of the inspection in a timely manner. The quality of the inspection data and the analysis or interpretation will greatly affect the level of risk mitigation."
Thus, inspection data quality and its correct analysis are directly linked to effective risk reduction.
[Reference: API 580, 2nd Edition (2016), Section 12.1, ===========, —]
API-580 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"