estimated risk before and after repairs and replacements.
B.
finding, listing, and characterizing elements of risk management.
C.
modifying inputs to the risk matrix.
D.
selecting and implementing measures to modify risk.
The Answer Is:
D
This question includes an explanation.
Explanation:
API 580 defines risk mitigation as follows:
“Risk mitigation: Process of selection and implementation of measures to modify risk. The term risk mitigation is sometimes used for measures themselves.”
This definition is provided in Section 3.1.67 of API 580. It is also emphasized throughout the document that mitigation may address either probability or consequence or both, and includes actions such as inspection, maintenance, repair, replacement, and design changes.
[Reference: API 580, 2nd Edition (2016), Section 3.1.67, ===========, —]
API-580 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"