process to find, list, and characterize elements of risk.
B.
systematic use of information to estimate risk and conduct risk evaluation.
C.
coordinated activities to direct and control risk in an organization.
D.
process used to assign values to the probability and consequence of risk.
The Answer Is:
B
This question includes an explanation.
Explanation:
As defined in Section 3.1.59 of API 580:
“Risk assessment: The systematic use of information to estimate risk and conduct risk evaluation.”
Option A refers more closely to hazard identification, C is the definition of risk management, and D describes part of the risk analysis process, but not the full definition of risk assessment.
[Reference: API 580, 2nd Edition (2016), Section 3.1.59, ===========]