What must be developed in order to implement and sustain the RBI program?
A.
Jurisdictional approval process
B.
Inspection plans for all equipment and piping in the RBI program
C.
Risk mitigation actions to reduce highest risks
D.
A documented management system
The Answer Is:
D
This question includes an explanation.
Explanation:
According to API 580, Section 16.1:
“A documented management system to implement and sustain an RBI program shall be developed and typically would include... procedures covering implementation, maintenance and reassessment, roles/responsibilities, documented assumptions, timeframe for applicability, and more.”
This is a minimum program requirement and foundational to RBI integrity.
[Reference: API 580, 2nd Edition (2016), Section 16.1, ===========, —]
API-580 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"