what planning strategies should be taken to make user acceptance testing (UAT) Efficient?
Execute all tests on behalf of the customer
Define and agree on acceptance criteria with customer
Issue change orders for all incidents that arise during testing
Train UAT testers on the new functionality
Finalize test plans before the build Phase completes
Efficient UAT in Revenue Cloud requires:
✔ B — Define acceptance criteria with the customerEnsures clarity on what “pass” means.
✔ D — Train UAT testers on the new functionalityUAT fails quickly if testers don’t know how to use CPQ/Billing.
✔ E — Finalize test plans before the build is completedEnsures UAT is ready and structured once the sandbox is available.
Incorrect options:
A: Consultants should NOT execute tests on behalf of customers.
C: Not all issues in UAT require change orders; many are defects to be corrected.