When initially creating MoSCoW priorities, what is the primary focus?
A.
Project priorities
B.
Project increment priorities
C.
Timebox priorities
D.
Iterative Development priorities
The Answer Is:
C
This question includes an explanation.
Explanation:
When initially creating MoSCoW priorities in AgilePM, the primary focus is on Timebox priorities. This approach ensures that each Timebox (a fixed period during which specific tasks must be completed) has clear and prioritized objectives. The MoSCoW method (Must have, Should have, Could have, Won't have this time) helps the team to deliver the most critical features within the given timeframe, thereby optimizing the value delivered in each iteration. This prioritization ensures that essential functionalities are completed first, making the project adaptable and resilient to changes.
References:
AgilePM Foundation Handbook
"Agile Project Management with Scrum" by Ken Schwaber
AgilePM-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 75% Discount on All Products,
Use Coupon: "ac75sure"