Which project elements can be used to measure a project’s adherence to its original schedule?

Which project elements can be used to measure a project’s adherence to its original schedule?

A.

Number of tasks, actual completion dates, and project status

B.

Project baselines, planned completion dates, and actual completion dates

C.

Workload balancer data, planned completion dates, and expenses