Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.

How can the project manager configure this relationship?

A.

Add a cross-project predecessor on the final milestone of Project 1.

B.

Add a cross-project predecessor on Task 1 in Project 1.

C.

Add a cross-project predecessor on the final milestone in Project 2.