What do the connector lines between tasks in a Gantt chart represent?
A.
Critical path
B.
Multiple assignments
C.
Predecessor relationship
The Answer Is:
C
This question includes an explanation.
Explanation:
In Workfront, the connector lines in a Gantt chart represent the predecessor relationships between tasks. These lines show how one task depends on another, indicating the order in which tasks need to be completed. This helps project managers visualize task dependencies and how changes in one task can affect others in the timeline.