A project manager needs to know the date that a task is likely to be...

A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.

Which date type would the project manager utilize?

A.

Estimated Date

B.

Projected Date

C.

Planned Date