A creative team accesses their assigned work in a My Tasks list report.

A creative team accesses their assigned work in a My Tasks list report. The team would like to easily see any New tasks highlighted for visibility. How can the project manager accommodate the team’s request?

A.

Schedule a daily automatic report delivery of the New tasks in the report to the team.

B.

Create a grouping for task Progress Status and use a custom color pie chart for visibility.

C.

Create a Filter that uses conditional formatting to display New tasks only.

D.

Create a View that uses Column Rules to format the New tasks for visibility.