Your team has been completing work on a fully estimated epic in each of the...

Your team has been completing work on a fully estimated epic in each of the last four sprints.

Your product owner wants you to predict how many additional sprints will be needed to complete it.

Which single report can provide the information?

A.

Epic Burndown

B.

Sprint Report

C.

Release Burndown

D.

Epic Report