Type IV-HT construction permits concealed spaces where those spaces comply with the specific protection alternatives prescribed for traditional heavy-timber construction. One permitted method is to completely fill the concealed space with noncombustible insulation. Therefore, option D is correct.
This provision should not be confused with the concealed-space requirements applicable to the tall mass timber classifications—Types IV-A, IV-B, and IV-C. Those classifications employ dedicated noncombustible protection and assigned-time requirements intended to control the contribution of concealed combustible construction during a fire. Type IV-HT follows a different concealed-space framework and allows protection through approved alternatives, including sprinkler protection, gypsum-board enclosure, or complete filling with noncombustible insulation, as applicable.
The insulation must completely occupy the concealed volume. Merely installing partial batt insulation, leaving unprotected voids, or relying on nominally fire-resistant thermal insulation does not satisfy the provision. The inspector should verify the material’s noncombustibility, continuity, placement around obstructions, and conformance with the approved construction documents before the space becomes inaccessible.
References/Topics: 2021 IBC Section 602.4.4; concealed spaces in Type IV-HT construction; noncombustible insulation protection method.
===============