A separate inspection by the building official is required where the fire resistance of a structural connection in Type IV-A, IV-B, or IV-C construction is provided by wood cover calculated in accordance with Section 2304.10.1. Therefore, option C is correct.
The required inspection occurs after the calculated wood cover has been installed but before additional coverings or finishes conceal the connection. This sequencing allows the building official to verify the actual cover thickness, geometry, continuity, fit, fastening, and correspondence with the approved fire-resistance design.
The requirement is distinct from routine Chapter 17 special inspection. Although a qualified special inspector may observe connection installation and mass timber erection, Section 110.3.5 expressly identifies a required building-department inspection for this calculated wood-cover condition. The inspection cannot be bypassed merely because the connection was observed during structural installation.
A rated joint system under Section 715 is governed by its tested or listed assembly requirements but is not the circumstance identified by this specific inspection provision. The other options do not state the code trigger. Inspectors should therefore coordinate notification before the connection is enclosed because subsequent destructive exposure may otherwise be necessary.
References/Topics: 2021 IBC Sections 110.3.5 and 2304.10.1; inspection of calculated wood cover protecting mass timber connections.
===============