Risk appetite directly affects what part of a vulnerability management program?
A.
Staff
B.
Scope
C.
Schedule
D.
Scan tools
The Answer Is:
B
This question includes an explanation.
Explanation:
Impact of Risk Appetite on Scope:
Risk appetite determines the extent of systems and vulnerabilities included in the program. A higher risk appetite may narrow the scope, focusing on critical systems, while a lower risk appetite might broaden it.
Tailoring to Organizational Goals:
By aligning the scope with risk appetite, organizations can prioritize efforts that meet their tolerance levels for risk.
Supporting Reference:
CCISO materials emphasize that the scope of vulnerability management should directly reflect the organization’s defined risk appetite.