Which of the following is considered a project versus a managed process?
A.
monitoring external and internal environment during incident response
B.
ongoing risk assessments of routine operations
C.
continuous vulnerability assessment and vulnerability repair
D.
installation of a new firewall system
The Answer Is:
D
This question includes an explanation.
Explanation:
Explanation:
Projects are temporary endeavors undertaken to create a unique product, service, or result. Installing a new firewall is a one-time task with a defined start and end point, fitting the definition of a project.
Managed processes, on the other hand, are ongoing activities, such as monitoring or continuous risk assessment.
Why Other Options Are Incorrect:
A. Monitoring external and internal environments: This is a continuous process.
B. Ongoing risk assessments: By definition, ongoing activities are managed processes.
C. Continuous vulnerability assessment and repair: Ongoing by nature and therefore a process.
EC-Council CISO Reference:
Differentiating between projects and managed processes is crucial for resource allocation and management in security operations.
712-50 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"