ECCouncil 712-50 Question Answer
At what level of governance are individual projects monitored and managed?
Program
Milestone
Enterprise
Portfolio
Governance Levels:
Individual projects are grouped under programs, which are monitored and managed collectively to achieve specific outcomes or benefits.
Program vs. Portfolio:
Programs consist of interrelated projects.
Portfolios include multiple programs and standalone projects aligned with strategic objectives.
Why Program Level:
Projects are tracked at the program level to ensure alignment with overarching goals and efficient resource allocation.