VMware 3V0-12.26 Question Answer
An architect has been engaged to design a new VMware Cloud Foundation (VCF) deployment for a customer that will provide platform-level high availability across three data centers to support their applications.
The customer has advised that there is high-bandwidth connectivity of 10 Gbps+ between the data centers, with less than 5 ms Round Trip Time (RTT) between each site, supporting a combination of Layer-2 and Layer-3 capabilities.
The customer has provided the following additional requirements:
A mix of Tier-1 (mission critical), Tier-2 (business critical), and Tier-3 (business operational) applications.
Tier-1 and Tier-2 applications require a Recovery Point Objective (RPO) of zero .
Compliance with all data sovereignty regulations.
Operational complexity must be reduced where possible.
Maximum Recovery Time Objective (RTO) of 24 hours in the event of a regional failure.
Given this information, which design should be recommended for the customer?