The network engineering team at a large corporation operates a critical data center with stringent business requirements for network reliability and high availability. EIGRP is used as an interior routing protocol. The team is planning to implement a robust new redundancy strategy that minimizes downtime and maximizes network uptime. According to the requirements, business services can tolerate 3 seconds for failover performance. The solution must be based on RFC 2281. Which action must the team take as part of the implementation?