A department manager submits a help desk ticket to request the migration of a printer's...

A department manager submits a help desk ticket to request the migration of a printer's port utilization from USB to Ethernet so multiple users can access the printer. This will be a new network printer; thus a new IP address allocation is required. Which of the following should happen immediately before network use is authorized?

A.

Document the date and time of the change.

B.

Submit a change request form.

C.

Determine the risk level of this change.

D.

Request an unused IP address.