What inputs should be considered when defining your OGL project scope and timelines?
A.
Fusion quarterly release schedule
B.
Email reminders from OGL console
C.
Availability of test user accounts
D.
Team member work schedules
The Answer Is:
A
This question includes an explanation.
Explanation:
The Fusion quarterly release schedule (option A) is a critical input for defining OGL project scope and timelines, as it dictates content updates and testing windows. Email reminders (option B), test user availability (option C), and team schedules (option D) are secondary or logistical, not scope-defining. The release schedule ensures alignment with application changes, anchoring the project’s temporal framework.